Biomass Power Facilities Idle for Months

One of bio­mass energy’s main sell­ing points is that it’s a base­load source of ener­gy avail­able 24/7, unlike solar and wind. Despite these promises–and hun­dreds of mil­lions of dol­lars of tax­pay­er sub­si­dies, grants and loans–several bio­mass pow­er facil­i­ties across the U.S. have been sit­ting idle for months at a time, thanks to fires, equip­ment fail­ure, and com­pe­ti­tion from cheap­er ener­gy sources.

Eagle Val­ley Clean Ener­gy – Gyp­sum, Colorado

Eagle Val­ley Clean Ener­gy, an 11.5‑megawatt bio­mass pow­er facil­i­ty in Gyp­sum, Col­orado began oper­a­tions in Decem­ber 2013, only to have its con­vey­or belt catch fire in Decem­ber 2014.

Despite assur­ances from facil­i­ty spokes­peo­ple that they’d resume oper­a­tions with­in a few months, the facil­i­ty is still offline as of Novem­ber 2015.

While Eagle Valley’s attor­ney recent­ly said they’d be up and run­ning again by the end of the year, the Town of Gyp­sum might not let that hap­pen, with town offi­cials point­ing out that the facil­i­ty had been oper­at­ing with­out a required cer­tifi­cate of occu­pan­cy, accord­ing to Vail Dai­ly.

Eagle Val­ley has received $40 mil­lion in loan guar­an­tees from the USDA, a por­tion of an annu­al $12.5 mil­lion match­ing pay­ment for feed­stock trans­porta­tion from the Bio­mass Crop Assis­tance Pro­gram (part of the Farm Bill), and a $250,000 bio­mass uti­liza­tion grant.

Gainesville Renew­able Ener­gy Cen­ter – Gainesville, Florida

The Gainesville Renew­able Ener­gy Cen­ter (GREC), a 100-megawatt bio­mass pow­er facil­i­ty in Gainesville, Flori­da, start­ed burn­ing wood chips for elec­tric­i­ty on Decem­ber 2013.

In August 2015, a light­ning strike caused the facil­i­ty to shut down tem­porar­i­ly, and when it became oper­a­tional again, Gainesville Region­al Util­i­ties (GRU) decid­ed not to bring it back online. Instead, GRU has relied on pow­er from Deer­haven Gen­er­at­ing Sta­tion, a coal plant that is “more eco­nom­ic than GREC’s facil­i­ty,” accord­ing to Mar­garet Craw­ford, GRU Com­mu­ni­ca­tions Director.

GRU pays about $39 per megawatt for elec­tric­i­ty from GREC, while GRU’s oth­er facil­i­ties gen­er­ate elec­tric­i­ty between $22 and $36 per megawatt, accord­ing to the Gainesville Sun.

On Novem­ber 4, Deer­haven shut down due to a leak in a steam-gen­er­at­ing tube, forc­ing GRU to bring GREC back online tem­porar­i­ly. GREC was tak­en offline again on Novem­ber 11, accord­ing to David Warm, Mar­ket­ing and Com­mu­ni­ca­tions for GRU. 

Nacog­doches Pow­er – Nacog­doches Texas

Nacog­doches Pow­er, a 100-megawatt bio­mass pow­er facil­i­ty owned by South­ern Pow­er Com­pa­ny in Nacog­doches, Texas, went online in June 2012, but was not oper­a­tional for a total of 17 months, as of July 2015 (the most recent data by the Ener­gy Infor­ma­tion Administration).

Austin Ener­gy pur­chas­es all of the pow­er from the facil­i­ty, which adds $2 a month to cus­tomers’ util­i­ty bills, accord­ing to the States­man.

Austin Ener­gy acknowl­edges the “dis­pro­por­tion­ate expense” of the facil­i­ty, and doesn’t plan to extend the twen­ty year contract.

Aspen Bio­mass – Lufkin, Texas

Aspen Bio­mass, a 50-megawatt bio­mass pow­er facil­i­ty owned by NRG Ener­gy Ser­vices in Lufkin, Texas came online in Sep­tem­ber 2011, sit­ting idle a total of 16 months over the next four years.

The facil­i­ty shut­down was blamed on “mar­ket eco­nom­ics,” accord­ing to Bio­mass Mag­a­zine.

WE Ener­gies – Roth­schild, Wisconsin

WE Ener­gies and Dom­tar Corp’s 50-megawatt bio­mass pow­er facil­i­ty opened in Roth­schild, Wis­con­sin in Novem­ber 2013.

After gen­er­at­ing no elec­tric­i­ty in Octo­ber 2014, it was tak­en offline from Decem­ber 2014 through May 2015 for repairs on the elec­tri­cal gen­er­at­ing steam tur­bine and leaks in the con­denser tubes. Dur­ing its first full year, it was oper­a­tional only 16% of the time, accord­ing to the Mil­wau­kee-Wis­con­sin Jour­nal Sen­tinel. Dur­ing this time, the facil­i­ty used more ener­gy than it generated.

“To run the plant would have been more cost­ly than oth­er options like run­ning our nat­ur­al gas plant or buy­ing pow­er on the mar­ket,” We Ener­gies spokesman Bri­an Man­they said, accord­ing to Mid­west Ener­gy News.

The facil­i­ty has report­ed­ly been oper­a­tional again since June 2015. 